Activity
Everything that changed across every job, newest first — what was ingested, decided, flagged, or acted on. The portfolio's running record of how the truth moved.
May 14, 2026 · 1 day ago
Current truth · AI confidence 91%
This job is at risk because the latest customer-approved drawings (Rev C) do not match the shop team's current working files (Rev B). Rev C revises the top-rail profile and adds two intermediate posts per run.
Current truth · AI confidence 85%
The install plan is stale. Three RFIs answered by Outlook in the last two weeks changed the anchor layout and sequence, but the PM schedule is unchanged since April 21.
Current truth · AI confidence 81%
A material substitution to a lighter gauge was discussed on the May 9 call to hold the budget, but the approved submittal still specifies the heavier gauge. The substitution is unconfirmed.
Ingested smartsheet export — Midtown_Schedule_Export_May_14.xlsx
Last modified Apr 21. No RFI tasks present in the schedule.
May 13, 2026 · 2 days ago
Current truth · AI confidence 80%
Stair fabrication is progressing but the welding specification cited verbally on the May 6 Teams coordination call has not been confirmed by the engineer of record. The shop drawing callout and the verbal note disagree.
Current truth · AI confidence 78%
Foundry Lofts is at risk because the balcony live-load rating differs between the customer requirements PDF and the structural sketch — fabrication detailing should not proceed until it is frozen.
Current truth · AI confidence 93%
Truss fabrication is aligned: the approved drawing set, the mill certs PDF, and the erection sequence confirmed by email all agree.
Current truth · AI confidence 95%
Davit and gangway fabrication is fully aligned across the approved load sheet, the finish email, and the confirmed delivery window.
Current truth · AI confidence 91%
Bollard fabrication is aligned: the crash-rated submittal, the foundation detail, and the surveyed layout all agree.
Current truth · AI confidence 76%
Atlas conveyor framing is at risk because a higher conveyor load requested in a May 10 email has not been reconciled with the approved frame design — detailing should hold.
Decision recorded
No further material cuts until the shop acknowledges Rev C.
Decision recorded
The approved IFC truss set is the single governing fabrication set.
Decision recorded
Marine-grade 316 stainless confirmed for all gangway and davit steel.
Decision recorded
Bollard crash rating and embedment per the approved submittal.
Ingested drawing — Riverside_Truss_Set_APPROVED.pdf
Approved long-span truss set. Erection sequence and crane pick plan confirmed by email.
Ingested pdf — Harbor_Davit_Load_Sheet.pdf
Davit working load and gangway live load confirmed. Hot-dip galvanized finish, delivery week of June 15.
Ingested pdf — Crossfield_Bollard_Submittal.pdf
Crash-rated bollard submittal approved; foundation detail and surveyed layout confirmed.
May 12, 2026 · 3 days ago
Current truth · AI confidence 77%
The shop drawing dimensions for the loading-dock handrail runs do not match the dimensions in the customer's May 11 Outlook update — a revision-control gap.
Current truth · AI confidence 96%
Gate fabrication is fully aligned across all sources. Profile, finish (satin black powder coat), and the install window are confirmed in writing on the SharePoint.
Current truth · AI confidence 78%
Stair-tower fabrication is mostly aligned, but the landing fire-rated assembly differs between the architectural spec and the May 8 coordination email — needs written confirmation.
Current truth · AI confidence 75%
Screen-wall detailing is progressing, but the wind-load basis mentioned on the May 7 Teams call has not been reconciled with the structural drawing — needs EOR confirmation.
Current truth · AI confidence 92%
Spiral-stair fabrication is aligned: the approved geometry, the field-verified shaft dimensions, and the finish are all confirmed in writing.
Conflict detected — RFI-Driven Scope Not in Schedule
Three RFIs answered by Outlook changed the anchor layout and sequence; the PM schedule is unchanged for 23 days.
Conflict detected — Anchor Type Discrepancy
RFI-014 sketch shows an epoxy anchor where the approved submittal shows a mechanical anchor.
Decision recorded
Latest answered RFI governs the anchor layout.
Decision recorded
Approved 3D geometry model governs the spiral stair fabrication.
Answered RFI-014
Revised anchor layout, adhesive anchors at slab edge — supersedes original.
Ingested spreadsheet — Harborline_RFI_Log.xlsx
Open RFIs: top-rail termination at stair, embed plate locations.
Ingested email — Midtown_RFI_014_Response.eml
Proceed with revised anchor layout per attached sketch. Revised detail indicates adhesive (epoxy) anchors at slab edge. This supersedes the original detail.
Ingested drawing — Granary_Spiral_Geometry_APPROVED.pdf
Approved spiral geometry; shaft dimensions field-verified and finish confirmed.
May 11, 2026 · 4 days ago
Current truth · AI confidence 74%
Canopy fabrication is on track but the corrosion-coating system is described two ways: the spec PDF calls for hot-dip galvanizing, the kickoff email says galvanize then powder coat.
Current truth · AI confidence 74%
Balustrade fabrication is mostly aligned, but the bronze patina described in customer emails ('warm, living finish') does not clearly match the approved finish-sample callout — needs confirmation.
Conflict detected — Shop Drawing vs. Customer Dimension Update
The customer's May 11 email gives loading-dock dimensions that differ from the current shop drawing set.
Decision recorded
Bronze patina not released until approved against the lobby mockup.
Issued dimension update
Dock handrail runs are 11'-4", not 10'-8" as drawn.
Ingested email — Apex_Dock_Dimensions_Update.eml
The dock handrail runs are 11'-4", not 10'-8" as previously drawn.
Ingested email — Belmont_Balustrade_Finish.eml
We want a warm, living bronze patina — please confirm it matches the approved finish sample.
May 10, 2026 · 5 days ago
Decision recorded
Gate finish is satin black powder coat over galvanized steel.
Decision recorded
Latest vendor load schedule governs conveyor frame detailing.
Ingested email — Briargrove_Gate_Approval.eml
Approved. Satin black powder coat over galvanized. Install window the week of June 1 works for us.
Ingested email — Atlas_Conveyor_Load_Increase.eml
Process engineering needs the conveyor support frames rated for a higher running load than the approved design.
May 9, 2026 · 6 days ago
Conflict detected — Drawing Revision Conflict — Rev B vs. Rev C
The customer approved Rev C while the shop folder marks Rev B as active, and a PM status report claims 70% fabrication complete — likely from the superseded drawing.
Conflict detected — Change Order Not Raised for Rev C Delta
Rev C increases the material take-off (added posts) but no change order has been raised; the contract value still reflects Rev B.
Conflict detected — Material Substitution vs. Approved Submittal
A lighter gauge was discussed on the May 9 call to hold budget, but the approved submittal still specifies the heavier gauge.
Requested substitution (verbal)
Asked on Teams to drop to lighter gauge to hold budget.
Decision recorded
Rev C is the approved drawing for railing fabrication.
Approved drawing revision
Approved Rev C — revised top rail, +2 intermediate posts per run.
Ingested drawing — Harborline_Railing_Rev_C_APPROVED.pdf
Approved — please proceed with Drawing Rev C as attached. Rev C revises the top-rail profile and adds two intermediate posts per run.
Ingested meeting transcript — Northgate_Budget_Call_Teams_May_9.txt
Customer: can we drop to the lighter gauge to keep the budget?
May 8, 2026 · 7 days ago
Decision recorded
Structural welds on hold pending written EOR weld-spec confirmation.
Decision recorded
Egress stair tread rating frozen pending fire-rated landing confirmation.
Ingested email — Maple_Stair_Coordination.eml
The landing assembly should be the two-hour rated build-up, please confirm against the architectural spec.
May 7, 2026 · 8 days ago
Decision recorded
Perforation pattern locked to the architect's approved pattern.
Ingested meeting transcript — Harborline_Coordination_Teams_May_7.txt
Discussion of Rev C impact on post count and install crew sizing. Action: PM to re-baseline date.
Ingested meeting transcript — Vertex_Screenwall_Teams_May_7.txt
Wind-load basis discussed verbally; to be reconciled with the structural drawing by the EOR.
May 6, 2026 · 9 days ago
Conflict detected — Weld Spec — Verbal Call vs. Drawing Callout
The May 6 Teams call note cites one weld spec; the approved shop drawing callout cites another. The EOR has not confirmed either in writing.
Conflict detected — Special Inspection Requirement Unconfirmed
If full-penetration welds govern, special inspection may be required and is not currently scheduled.
Verbal weld instruction
Said on Teams: 'go with the full-pen detail on stringer connections.'
Decision recorded
Stringer connection detail 4/S-301 governs unless EOR supersedes.
Ingested meeting transcript — Beacon_Stair_Coordination_Teams_May_6.txt
EOR (verbal): go with the full-pen detail on the stringer connections. No special-inspection scheduling discussed.
May 5, 2026 · 10 days ago
Conflict detected — Install Date Promised on Superseded Revision
The PM committed a May 27 install date based on Rev B progress. Rev C adds posts and revises the top rail, changing labor and material.
Committed shop revision
Shop drawings to Rev C by Wednesday (May 13).
Committed install date
Locked May 27 install based on ~70% progress (Rev B basis).
Ingested email — Harborline_Railing_PM_Status.eml
Railing fabrication is approximately 70% complete. Install is locked for May 27 based on current progress. Shop will be on Rev C by Wednesday.
May 2, 2026 · 13 days ago
Annotated structural sketch
Balcony framing annotated 100 psf — conflicts with 60 psf in requirements PDF.
Ingested drawing — Foundry_Lofts_Structural_Sketch.pdf
Balcony framing annotated 100 psf live load. Members sized accordingly.
Apr 30, 2026 · 15 days ago
Ingested drawing — MetalWorks_Harborline_Railing_Rev_B.pdf
Rev B drawing set. Marked ACTIVE in the shop folder. Top-rail profile and post spacing differ from Rev C.
Apr 29, 2026 · 16 days ago
Ingested email — Lakeside_Canopy_Kickoff.eml
We want it galvanized and then powder coated in the bronze color.
Apr 28, 2026 · 17 days ago
Issued shop drawing callout
Connection callout: fillet weld per detail 4/S-301.
Ingested drawing — Beacon_Stair_Shop_Drawing_S-301.pdf
Connection callout: fillet weld per detail 4/S-301. General notes reference special inspection per IBC where applicable.
Apr 26, 2026 · 19 days ago
Conflict detected — Coating System Conflict
Spec PDF calls for hot-dip galvanizing only; the kickoff email says galvanize then powder coat.
Ingested pdf — Lakeside_Canopy_Spec.pdf
All exposed steel hot-dip galvanized per ASTM A123.
Apr 25, 2026 · 20 days ago
Ingested pdf — Harborline_Railing_Spec_Section_05.pdf
Metal railing spec: hot-dip galvanize then shop prime. Field-verify slab edge prior to install.
Apr 24, 2026 · 21 days ago
Ingested drawing — Apex_Pipe_Handrail_Shop_Set.pdf
Dock handrail runs dimensioned 10'-8" on current set.
Apr 22, 2026 · 23 days ago
Conflict detected — Balcony Live-Load Rating Mismatch
The customer requirements PDF states 60 psf; the structural sketch annotates 100 psf. Detailing should not proceed until frozen.
Ingested pdf — Foundry_Lofts_Requirements.pdf
Juliet balconies designed for 60 psf live load. Exterior stair galvanized.
Apr 20, 2026 · 25 days ago
Ingested pdf — Beacon_Stair_Requirements.pdf
Monumental stair: stringers, treads, landings. Connection per EOR.
Apr 18, 2026 · 27 days ago
Ingested pdf — Midtown_Approved_Submittal.pdf
Submittal specifies mechanical expansion anchors at slab edge.
Apr 15, 2026 · 1 month ago
Ingested pdf — Northgate_Approved_Submittal.pdf
Cladding panels: heavier gauge aluminum, approved as submitted.