Approvals
Everything across every job that's waiting on a human decision — who it's with, how long it's been sitting, and what it costs if it keeps waiting.
11
awaiting approval
$347,700
exposure waiting on a decision
4 weeks
oldest item waiting
Material Substitution vs. Approved Submittal
Issue a formal substitution request and get written approval before cutting.
Anchor Type Discrepancy
Confirm anchor type and update the submittal before procurement.
Balcony Live-Load Rating Mismatch
Freeze the governing rating with Anvil's EOR before releasing detailing.
Shop Drawing vs. Customer Dimension Update
Reconcile the May 11 dimensions into the shop set and confirm the active revision.
Coating System Conflict
Confirm the governing coating system with the architect before blasting.
Weld Spec — Verbal Call vs. Drawing Callout
Obtain written EOR confirmation of the governing weld spec before structural welds proceed.
Special Inspection Requirement Unconfirmed
Confirm inspection requirements with the EOR alongside the weld spec.
Drawing Revision Conflict — Rev B vs. Rev C
Pause work, make Rev C the single active revision, and issue a priced change order for the delta.
Change Order Not Raised for Rev C Delta
Quantify the Rev C delta and raise a change order before proceeding.
Install Date Promised on Superseded Revision
Re-baseline the install date against Rev C and communicate proactively before the GC plans crews.
RFI-Driven Scope Not in Schedule
Reconcile RFI outcomes into the schedule and confirm the sequence with the superintendent.