Demo Mode
MW

Agent

Truth Finder works while you don't. It sweeps every connected source on a schedule, drafts the low-risk replies itself, and only escalates what genuinely needs your call to the inbox on the right.

917

checks run (last 24h)

3

responses auto-drafted

16

need a human

last run 2026-05-16 06:00:00

Agent activity log

Morning sweep

2026-05-16 06:00:00
312 checks38 sources2 flagged2 auto-drafted

Swept 38 sources across 20 jobs. 1 critical conflicts still open; auto-drafted 2 clarification emails and 1 change order for review.

  • Drawing Revision Conflict — Rev B vs. Rev C Auto-drafted clarification — awaiting human send · Harborline Tower

Overnight deep scan

2026-05-16 02:00:00
318 checks38 sources5 flagged1 auto-drafted

Overnight hybrid re-index + cross-reference. 4 commitments went overdue; 5 high-severity conflicts re-confirmed against the latest evidence.

  • Overdue: Shop drawings will be revised to Rev C by Wednesday. Escalated to triage · Harborline Tower
  • Overdue: PM will get written weld-spec confirmation from the EOR. Escalated to triage · Beacon Plaza

End-of-day reconcile

2026-05-15 18:00:00
287 checks37 sources2 flagged0 auto-drafted

Reconciled evidence vs. schedule. Plan drift detected on 2 jobs; no auto-actions taken — both routed to humans.

  • Plan drift — schedule stale vs. RFI scope Routed to PM · Midtown Exchange

Needs a human (16)

CriticalConflictHarborline Tower

Drawing Revision Conflict — Rev B vs. Rev C

The customer approved Rev C while the shop folder marks Rev B as active, and a PM status report claims 70% fabrication complete — likely from the superseded drawing.

Pause work, make Rev C the single active revision, and issue a priced change order for the delta.

Cost of being wrong: $29,100–$51,100

CriticalCommitmentHarborline Tower

Shop drawings will be revised to Rev C by Wednesday.

Owed by Dale Forsythe (Shop Lead) · due 2026-05-13 · not in the plan

Convert to a scheduled task with an owner today.

CriticalCommitmentBeacon Plaza

PM will get written weld-spec confirmation from the EOR.

Owed by Project Manager · due 2026-05-12 · not in the plan

Convert to a scheduled task with an owner today.

CriticalRequirementHarborline Tower

Fabricate from latest approved drawing revision

Fabrication must follow the latest customer-approved drawing revision (Rev C), not the shop's working Rev B. (confidence 92%)

Freeze in writing with the responsible engineer before release.

CriticalRequirementBeacon Plaza

Governing weld specification

Structural welds must follow the engineer-of-record-confirmed weld spec, not an unconfirmed verbal note. (confidence 49%)

Freeze in writing with the responsible engineer before release.

CriticalRequirementFoundry Lofts

Balcony live-load rating

Juliet balconies must meet the governing live-load rating. (confidence 51%)

Freeze in writing with the responsible engineer before release.

CriticalRequirementMaple Court

Fire-rated landing detail confirmation

The fire-rated landing detail described in the May 8 email must be confirmed against the approved shop drawing. (confidence 58%)

Freeze in writing with the responsible engineer before release.

CriticalRequirementVertex Data Center

Wind-load attachment criteria frozen

Rooftop screen-wall panel attachment must follow the governing wind-load criteria, confirmed by the EOR. (confidence 55%)

Freeze in writing with the responsible engineer before release.

CriticalRequirementAtlas Foods

Frames detailed to governing load schedule

Conveyor support frames must be detailed to the governing (latest vendor) load schedule. (confidence 64%)

Freeze in writing with the responsible engineer before release.

HighConflictHarborline Tower

Install Date Promised on Superseded Revision

The PM committed a May 27 install date based on Rev B progress. Rev C adds posts and revises the top rail, changing labor and material.

Re-baseline the install date against Rev C and communicate proactively before the GC plans crews.

Cost of being wrong: $20,600–$34,100

HighConflictBeacon Plaza

Weld Spec — Verbal Call vs. Drawing Callout

The May 6 Teams call note cites one weld spec; the approved shop drawing callout cites another. The EOR has not confirmed either in writing.

Obtain written EOR confirmation of the governing weld spec before structural welds proceed.

Cost of being wrong: $29,700–$44,100

HighConflictMidtown Exchange

RFI-Driven Scope Not in Schedule

Three RFIs answered by Outlook changed the anchor layout and sequence; the PM schedule is unchanged for 23 days.

Reconcile RFI outcomes into the schedule and confirm the sequence with the superintendent.

Cost of being wrong: $21,600–$33,600

HighConflictFoundry Lofts

Balcony Live-Load Rating Mismatch

The customer requirements PDF states 60 psf; the structural sketch annotates 100 psf. Detailing should not proceed until frozen.

Freeze the governing rating with Anvil's EOR before releasing detailing.

Cost of being wrong: $39,100–$54,700

HighConflictNorthgate Mall

Material Substitution vs. Approved Submittal

A lighter gauge was discussed on the May 9 call to hold budget, but the approved submittal still specifies the heavier gauge.

Issue a formal substitution request and get written approval before cutting.

Cost of being wrong: $17,800–$30,000

MediumCommitmentMidtown Exchange

Field will confirm anchor type with the superintendent.

Owed by Field Lead · due 2026-05-13 · not in the plan

Convert to a scheduled task with an owner today.

MediumCommitmentLakeside Pavilion

PM will confirm the coating system with the architect.

Owed by Project Manager · due 2026-05-14 · not in the plan

Convert to a scheduled task with an owner today.

Every auto-action is logged to the immutable audit trail.