9 entries · immutableGreg Mason · Answered RFI-014
Revised anchor layout, adhesive anchors at slab edge — supersedes original.
Lydia Chen · Issued dimension update
Dock handrail runs are 11'-4", not 10'-8" as drawn.
Carl Jensen · Requested substitution (verbal)
Asked on Teams to drop to lighter gauge to hold budget.
Ray Donnelly · Approved drawing revision
Approved Rev C — revised top rail, +2 intermediate posts per run.
Susan Park, PE · Verbal weld instruction
Said on Teams: 'go with the full-pen detail on stringer connections.'
Dale Forsythe · Committed shop revision
Shop drawings to Rev C by Wednesday (May 13).
Karen Liu · Committed install date
Locked May 27 install based on ~70% progress (Rev B basis).
Daniel Brooks, PE · Annotated structural sketch
Balcony framing annotated 100 psf — conflicts with 60 psf in requirements PDF.
Marcus Reed · Issued shop drawing callout
Connection callout: fillet weld per detail 4/S-301.