9 entries · immutable

Greg Mason · Answered RFI-014

Revised anchor layout, adhesive anchors at slab edge — supersedes original.

May 12, 2026·Midtown Exchange

Lydia Chen · Issued dimension update

Dock handrail runs are 11'-4", not 10'-8" as drawn.

May 11, 2026·Apex Logistics

Carl Jensen · Requested substitution (verbal)

Asked on Teams to drop to lighter gauge to hold budget.

May 9, 2026·Northgate Mall

Ray Donnelly · Approved drawing revision

Approved Rev C — revised top rail, +2 intermediate posts per run.

May 9, 2026·Harborline Tower

Susan Park, PE · Verbal weld instruction

Said on Teams: 'go with the full-pen detail on stringer connections.'

May 6, 2026·Beacon Plaza

Dale Forsythe · Committed shop revision

Shop drawings to Rev C by Wednesday (May 13).

May 5, 2026·Harborline Tower

Karen Liu · Committed install date

Locked May 27 install based on ~70% progress (Rev B basis).

May 5, 2026·Harborline Tower

Daniel Brooks, PE · Annotated structural sketch

Balcony framing annotated 100 psf — conflicts with 60 psf in requirements PDF.

May 2, 2026·Foundry Lofts

Marcus Reed · Issued shop drawing callout

Connection callout: fillet weld per detail 4/S-301.

Apr 28, 2026·Beacon Plaza