Midtown Exchange — Commercial Handrail Install
Outdated PlanHarborline GC · Construction · Last source update May 14, 2026
63
High
risk score
Current truth
The install plan is stale. Three RFIs answered by Outlook in the last two weeks changed the anchor layout and sequence, but the PM schedule is unchanged since April 21.
AI confidence85%
Source coverage74%
Open questions
- Does RFI-014 push the topping-out milestone, and is the GC aware?
Next recommended action
Reconcile RFI-driven scope into the schedule and confirm the revised install sequence with the GC superintendent.
Resolve in Chat
7
Confirmed requirements
3
Open requirements
2
Conflicts
2
Untracked commitments
Summary
Commercial handrail and guardrail install for a GC. The schedule has not moved in 23 days while three field RFIs changed the anchor layout and install sequence.