Beacon Plaza Monumental Stair — Structural Coordination
MeetGeek AI summary
The EOR verbally directed the shop to use the full-penetration weld detail on the stringer connections. This was a verbal instruction only; no written confirmation or revised drawing was issued on the call. Special inspection scheduling was not discussed.
AI-extracted action items
- Susan Park — issue written weld-spec confirmation
- Karen Liu — obtain written EOR confirmation (due Mon May 12)
- Tom Alvarez — hold structural welds until confirmed
Transcript
Susan Park · 14:45
For the stringer-to-landing connections, go with the full-pen detail, not the fillet shown. I'll get you something in writing but proceed on that basis.
Tom Alvarez · 16:02
We'll hold structural welds until we have the spec in writing — I don't want to weld a monumental stair off a call.
Karen Liu · 17:30
Agreed. I'll chase the written confirmation from Susan.
Document
Susan Park, PEEngineer of Record · Park Structural
Extracted from this document (6)