Schedule export · Midtown Exchange

Document viewer

The source as it was actually received — with the spans Truth Finder extracted into requirements, conflicts, and decisions highlighted in place.

SharePoint · Smartsheet Export

Midtown_Schedule_Export_May_14.xlsx

Source system: Smartsheet (PM tool sync)Export generated: May 14, 2026
Schedule last modified: Apr 21, 2026
Findings:
• No tasks reference RFI-012, RFI-013, or RFI-014.
• Anchor-set task still sequenced before slab-edge survey (pre-RFI logic).
• 23 calendar days since the schedule was last edited, while 3 RFIs in the
same window changed anchor scope and sequence.

Document

Karen LiuProject Manager · Metal Works

Governingreliability 95%