Outlook thread · Harborline Tower
Document viewer
The source as it was actually received — with the spans Truth Finder extracted into requirements, conflicts, and decisions highlighted in place.
Outlook · 2026-05-05
Harborline railing — weekly status
KL
Karen Liu <kliu@metalworks.example>
to Ray Donnelly <ray.donnelly@harborline-gc.example>
Ray,
Quick status before our Thursday sync:
• Railing fabrication is approximately 70% complete. • Install is locked for May 27 based on current fabrication progress. • Shop will be on Rev C by Wednesday (Dale is re-detailing now).
No blockers from our side at this time.
Karen Liu Project Manager, Metal Works
Truth Finder note · This status was written before Rev C was formally approved on May 9. The 70%
figure and the May 27 date are both on the Rev B basis.
Document
Karen LiuProject Manager · Metal Works
Supersededreliability 75%
PM status reported progress and the install date on the Rev B basis, before Rev C was approved on May 9.