Harborline Railing — Coordination Call
MeetGeek AI summary
The team discussed the impact of Rev C on post count and install crew sizing. Rev C adds two intermediate posts per run, which increases weld and finishing labor. Karen committed to re-baselining the install date against Rev C.
AI-extracted action items
- Karen Liu — re-baseline install date vs. Rev C (due Fri May 15)
- Dale Forsythe — confirm added-post fabrication hours
Transcript
Ray Donnelly · 03:11
Just confirming you all have Rev C — the added posts are not optional, the architect wants them.
Dale Forsythe · 04:02
We have it. It's roughly two extra posts per run, so more weld-out and more galv hooks. Not trivial.
Karen Liu · 05:20
Understood. I'll re-baseline the install date against Rev C and get you a realistic date by Friday.
Document
Karen LiuProject Manager · Metal Works