Harborline Railing — Coordination Call

Platform: Microsoft Teams · May 7, 2026 · 27 min · Participants: Karen Liu (Metal Works), Dale Forsythe (Metal Works),

MeetGeek AI summary

The team discussed the impact of Rev C on post count and install crew sizing. Rev C adds two intermediate posts per run, which increases weld and finishing labor. Karen committed to re-baselining the install date against Rev C.

AI-extracted action items

  • Karen Liu — re-baseline install date vs. Rev C (due Fri May 15)
  • Dale Forsythe — confirm added-post fabrication hours

Transcript

RD

Ray Donnelly · 03:11

Just confirming you all have Rev C — the added posts are not optional, the architect wants them.

DF

Dale Forsythe · 04:02

We have it. It's roughly two extra posts per run, so more weld-out and more galv hooks. Not trivial.

KL

Karen Liu · 05:20

Understood. I'll re-baseline the install date against Rev C and get you a realistic date by Friday.